How Much Concrete Do I Need for a Column or Deck Pier? Use the Radius, Not the Diameter

Deck piers, fence posts set in concrete and round columns all use the same cylinder formula. Measure the diameter and the height, and the rest is simple arithmetic.

The formula

Volume = π × radius² × height, with the radius in feet (diameter ÷ 24), then ÷ 27 for cubic yards, multiplied by the number of identical columns.

A worked example: a single 12 in diameter pier, 4 ft deep

  • Radius: 12 in ÷ 24 = 0.5 ft
  • Volume: 3.1416 × 0.25 × 4 = 3.14 cubic feet
  • Cubic yards: 3.14 ÷ 27 = 0.12 cubic yards
  • Bags: 6 × 80 lb bags with 10% waste

A taller 16 in diameter column, 8 ft high, is 11.17 cubic feet = 0.41 cubic yards, 21 bags with waste.

The common mistake

The common mistake is using the diameter instead of the radius — that quadruples the result. Always halve the diameter first.

Waste and fence posts

Set a 10% waste margin (15% for hand-dug holes in loose soil); dug holes are rarely perfect cylinders. For fence posts, subtract the post volume if it is large — a 4×4 post in a 12 in hole displaces about 0.05 cubic feet per foot. Go below the frost line, typically 36–48 in depending on climate.

If you would rather not do the arithmetic by hand, run the same numbers through a column concrete calculator — it handles one pier or a whole row in one step.